Methodist Hospital

Medical (OSHPD & VA) Projects

Methodist Hospital ED Expansion and ASW
Sacramento, CA
Design-Assist
Contract Amount: $3,700,000

Emergency Center and Trauma Center Expansion: This project consisted of a 20-bed expansion to the Emergency Department, including the renovation of the existing Emergency Department Registration, Triage, and Radiology Departments, and the physical addition of a new Emergency Department Exam and Treatment Suite. A new 64-slice CT Scan was installed in a new CT Suite. The expansion included approximately 12,000 square feet in the new addition, plus the renovation to an existing 10,000 square feet.

Area Separation Walls and SPC-2 Seismic Upgrades: This project consisted of retrofitting existing walls throughout the East Wing to create a 2-hour fire rated area separation wall and shear walls.